QualEngine Training / Design Record
P2 · Training · PPAP element 01 / Design record

Design recordDesign Record

Definition

A design record is PPAP element 01: the supplier must provide, for the production part, released engineering records (drawing, CAD model, specifications), includingall of its details, and applyballoon numberingon the drawing, so that every characteristic corresponds consistently across the drawing, Control Plan, process flow diagram, PFMEA and PSW. Any engineering change must be recorded as a new revision and entered in the ledger, ensuring that mass production is based on the latest released revision.

AIAG PPAP (4th edition), element 01 IATF 16949 · 8.3.5.1 Design output ASME Y14.5 Dimensioning and tolerancing

1. Definition and purpose

Why a "released record" and not "one drawing"

PPAP element 01 requires that, for the production part, released engineering records be provided (drawing, CAD model, specifications), andall of its details not just a single drawing handed over. The reason is that PPAP submits "the set of records it was built from", and the Control Plan, PFMEA, process flow diagram and PSW all take their characteristics from it; if any category is missing (for example only the drawing, without the material specification), downstream has no complete design basis.

Two points are critical: first, itmust be the customer-released revision— a prototype drawing or an unreleased internal drawing does not constitute a valid design record; second, itmust carry balloon numbers— every characteristic on the drawing must be marked with a number (①, ②, …) so that it maps one to one to the same characteristic in the Control Plan, PFMEA, process flow diagram and PSW.

Four questions the design record must answer

QuestionAnswer given by the record
What is recordedProduction part drawing (with all dimensions and GD&T), CAD model, material specification
Is the revision correctThe drawing revision (for example C) matches the CAD model revision and is the current customer-released revision
Do the numbers share one sourceBalloon numbers ①②③… match the CP characteristic number, PFMEA item, Flow step and PSW result
Is the change controlledAfter an ECN the revision is updated and entered in the ledger, and the old revision is marked "obsolete" and not mixed in

2. Record types and numbering rules

Fix the type first, then number

A design record is not one file but a set of engineering records that corroborate each other.Production part drawingis the main body,the CAD modelreflects the geometry,the material / performance specificationdefines the material and acceptance criteria,Special characteristicsmust carry symbol marking,after an engineering changethe whole set is re-released. If any category is missing or the revisions disagree, the set is incomplete.

TypeContentNumbering rule
Production part drawingCustomer-released part drawing with all dimensions, GD&T and datumsOne drawing number + revision per drawing; characteristics use balloon numbers ① ~ Ⓝ
the CAD model3D CAD model and coordinate datumsThe model revision corresponds to the drawing revision, and feature IDs match the balloon numbers
Material / specificationMaterial grade, standard, performance lower limitRecorded as a separate item citing the same standard as the material field on the drawing
Special characteristicsCustomer-designated special characteristic symbolsThe same symbol is consistent on the drawing and in the CP, with numbers from one source
after an engineering changeNew revision records after an ECNA revision change must be entered in the ledger, and the old revision is marked "obsolete" and not mixed in
Production part drawing the CAD model Balloon numbers ① ② ③ Control Plan CP Process flow diagram (Flow) PFMEA PSW results Numbers from one source — the same characteristic carries the same number in the four documents
Figure 2-1 Design record linked to the Control Plan, flow diagram, PFMEA and PSW by balloon numbers
What to do when the CAD model and the drawing disagree

In practice the CAD model and the 2D drawing often fail to match.It must be declared which one governs(usually designated by the customer in the drawing title block or the technical agreement), and the differences must be confirmed in writing and archived; otherwise production and inspection each follow their own version, and every capability study and Control Plan based on the record loses its common basis.

3. Balloon numbering and traceability

Number first, then link

On the drawing, in the order ①, ②, …, give each studied characteristic aballoon numberingand the number of ledger rows equals the number of recorded characteristics, one to one. Going straight to the Control Plan without numbering easily produces the situation where "the CP lists 5 characteristics, the drawing marks 7, and the PFMEA uses yet another set of numbers" — the traceability chain breaks and complete coverage cannot be demonstrated at a customer audit.

Balloon numbers on the drawing ① Outer diameter Ø25 25±0.05 ② Hardness HBW ≥170 ③ Position ⏀Φ0.1 A Design record ledger (rows = number of characteristics) One source The same number in downstream documents CP characteristic No. ① / ② / ③ ← Control Plan Flow step → PFMEA failure item → PSW result Special characteristic symbols are marked consistently on the drawing and in the CP One set of numbers running through four documents
Figure 3-1 Balloon numbers (①②③…) share one source across the Control Plan, flow diagram, PFMEA and PSW

Numbering and registration discipline

Full coverageEvery studied characteristic on the drawing is numbered, and the ledger rows match it.
UniquenessNumbers are not repeated within one ledger, so traceability and customer checking stay easy.
Common sourceThe CP characteristic number, Flow step, PFMEA item and PSW result all cite the same number.
Closed loopAfter an engineering change the revision is updated and the numbers re-marked, the old revision is marked obsolete, and the revision record is traceable.

4. Sign-off and revision control

The design record ledger is also a controlled document

The design record ledger is acontrolled document(IATF 16949 7.5.3 control of documented information): the current revision is controlled, obsolete revisions are withdrawn, and revisions are recorded. None of the three may be missing:

Three-level sign-offPrepared (product / design engineer) → reviewed (design supervisor) → approved (technical owner), with signature + title + date.
Revision identificationThe revision number rises with each revision (A / 0 → A / 1 or B / 0), and users only ever see the current revision.
Revision recordRevision content, date, reviser and approver are traceable for every revision.

Sign-off page style (the same one built into the workbench)

ResponsibilityName (signature)TitleDateComment
Prepared by
Reviewed by
Approved by

The sign-off order cannot skip a level: preparation must be complete before review, and review must pass before approval. After an engineering change, the original approver (or a delegate) approves again. Once the three-level sign-off is complete, the record is submitted as PPAP element 01 together with the other documents.

5. Common mistakes

Five frequent mistakes

① Submitting a prototype or unreleased revision (it must be the customer-released production part drawing); ② balloon numbers do not correspond to the CP / PFMEA characteristic numbers, breaking traceability; ③ only part of the content is submitted (missing GD&T, missing datums, missing material specification); ④ after an engineering change the old revision is still in use, neither re-released nor marked obsolete; ⑤ the CAD model and drawing disagree without declaring which one governs.

Pre-submission checklist

What is submitted is the customer-released "production part" drawing, not a prototype / unreleased revision.
The drawing contains all dimensions, GD&T and datums, and matches the CAD model.
Every characteristic has a balloon number, and the drawing-CP-PFMEA-Flow-PSW numbers share one source.
The material specification is complete and special characteristic symbols are consistent on the drawing and in the CP.
The engineering change has been re-released and entered in the ledger, and the old revision is marked obsolete; the record is signed off at three levels and submitted as PPAP element 01.

6. Self-test

Self-test (5 questions)

Q1What does PPAP element 01 "design record" require to be submitted?
Any internal drawingA sketch from the prototype stageCustomer-released engineering records for the production part, including all of its details
It must be the customer-released production part drawing together with its CAD model and specifications; a prototype drawing or an unreleased revision is not a valid design record.
Q2What is the main purpose of balloon numbers (①, ②, …)?
To mark the sequence of operationsTo make every characteristic on the drawing cite the same number as the Control Plan, PFMEA and PSWTo make the drawing look nicer
The key to balloon numbers is "one source": the same characteristic carries the same number in the drawing, CP, Flow, PFMEA and PSW, so the traceability chain is never broken.
Q3After an engineering change (ECN), how should the design record ledger be handled?
Re-release it and enter it in the ledger, marking the old revision "obsolete" and not mixing themKeep using the old revisionChange only the drawing and leave the ledger alone
After a change the revision must be updated, the ledger updated and the numbers re-marked; the old revision is marked obsolete and withdrawn, otherwise the floor will work from an outdated drawing.
Q4When the CAD model and the 2D drawing disagree, the correct action is to
Just take the CAD model as governingNo action is neededConfirm the differences in writing and declare which governs, asking the customer to confirm and archiving it where necessary
Failing to declare the basis makes production and inspection each follow their own version; which one governs must be made explicit (usually designated by the customer) and recorded in writing.
Q5What should the relationship be between ledger rows and the design record?
Fill it in at willRows = number of recorded characteristics, with numbers matched one to oneA fixed 10 rows
One number per characteristic; the number of rows equals the number of recorded characteristics, and the numbers match the drawing balloon numbers and CP characteristic numbers one to one.

Hands-on practice: Design Record workbench

OpenDesign Record workbench, register the characteristic list of a drawing as ①, ②, … (with revision and source) and watch how the "Completeness" column validates the required fields in real time; then return toPPAP 18-element ledgerto track the remaining elements.

Based on the AIAG PPAP Manual (4th edition) / IATF 16949:2016 / ASME Y14.5