Design recordDesign Record
A design record is PPAP element 01: the supplier must provide, for the production part, released engineering records (drawing, CAD model, specifications), includingall of its details, and applyballoon numberingon the drawing, so that every characteristic corresponds consistently across the drawing, Control Plan, process flow diagram, PFMEA and PSW. Any engineering change must be recorded as a new revision and entered in the ledger, ensuring that mass production is based on the latest released revision.
1. Definition and purpose
Why a "released record" and not "one drawing"
PPAP element 01 requires that, for the production part, released engineering records be provided (drawing, CAD model, specifications), andall of its details not just a single drawing handed over. The reason is that PPAP submits "the set of records it was built from", and the Control Plan, PFMEA, process flow diagram and PSW all take their characteristics from it; if any category is missing (for example only the drawing, without the material specification), downstream has no complete design basis.
Two points are critical: first, itmust be the customer-released revision— a prototype drawing or an unreleased internal drawing does not constitute a valid design record; second, itmust carry balloon numbers— every characteristic on the drawing must be marked with a number (①, ②, …) so that it maps one to one to the same characteristic in the Control Plan, PFMEA, process flow diagram and PSW.
Four questions the design record must answer
| Question | Answer given by the record |
|---|---|
| What is recorded | Production part drawing (with all dimensions and GD&T), CAD model, material specification |
| Is the revision correct | The drawing revision (for example C) matches the CAD model revision and is the current customer-released revision |
| Do the numbers share one source | Balloon numbers ①②③… match the CP characteristic number, PFMEA item, Flow step and PSW result |
| Is the change controlled | After an ECN the revision is updated and entered in the ledger, and the old revision is marked "obsolete" and not mixed in |
2. Record types and numbering rules
Fix the type first, then number
A design record is not one file but a set of engineering records that corroborate each other.Production part drawingis the main body,the CAD modelreflects the geometry,the material / performance specificationdefines the material and acceptance criteria,Special characteristicsmust carry symbol marking,after an engineering changethe whole set is re-released. If any category is missing or the revisions disagree, the set is incomplete.
| Type | Content | Numbering rule |
|---|---|---|
| Production part drawing | Customer-released part drawing with all dimensions, GD&T and datums | One drawing number + revision per drawing; characteristics use balloon numbers ① ~ Ⓝ |
| the CAD model | 3D CAD model and coordinate datums | The model revision corresponds to the drawing revision, and feature IDs match the balloon numbers |
| Material / specification | Material grade, standard, performance lower limit | Recorded as a separate item citing the same standard as the material field on the drawing |
| Special characteristics | Customer-designated special characteristic symbols | The same symbol is consistent on the drawing and in the CP, with numbers from one source |
| after an engineering change | New revision records after an ECN | A revision change must be entered in the ledger, and the old revision is marked "obsolete" and not mixed in |
In practice the CAD model and the 2D drawing often fail to match.It must be declared which one governs(usually designated by the customer in the drawing title block or the technical agreement), and the differences must be confirmed in writing and archived; otherwise production and inspection each follow their own version, and every capability study and Control Plan based on the record loses its common basis.
3. Balloon numbering and traceability
Number first, then link
On the drawing, in the order ①, ②, …, give each studied characteristic aballoon numberingand the number of ledger rows equals the number of recorded characteristics, one to one. Going straight to the Control Plan without numbering easily produces the situation where "the CP lists 5 characteristics, the drawing marks 7, and the PFMEA uses yet another set of numbers" — the traceability chain breaks and complete coverage cannot be demonstrated at a customer audit.
Numbering and registration discipline
4. Sign-off and revision control
The design record ledger is also a controlled document
The design record ledger is acontrolled document(IATF 16949 7.5.3 control of documented information): the current revision is controlled, obsolete revisions are withdrawn, and revisions are recorded. None of the three may be missing:
Sign-off page style (the same one built into the workbench)
| Responsibility | Name (signature) | Title | Date | Comment |
|---|---|---|---|---|
| Prepared by | ||||
| Reviewed by | ||||
| Approved by |
The sign-off order cannot skip a level: preparation must be complete before review, and review must pass before approval. After an engineering change, the original approver (or a delegate) approves again. Once the three-level sign-off is complete, the record is submitted as PPAP element 01 together with the other documents.
5. Common mistakes
① Submitting a prototype or unreleased revision (it must be the customer-released production part drawing); ② balloon numbers do not correspond to the CP / PFMEA characteristic numbers, breaking traceability; ③ only part of the content is submitted (missing GD&T, missing datums, missing material specification); ④ after an engineering change the old revision is still in use, neither re-released nor marked obsolete; ⑤ the CAD model and drawing disagree without declaring which one governs.
Pre-submission checklist
6. Self-test
Self-test (5 questions)
Hands-on practice: Design Record workbench
OpenDesign Record workbench, register the characteristic list of a drawing as ①, ②, … (with revision and source) and watch how the "Completeness" column validates the required fields in real time; then return toPPAP 18-element ledgerto track the remaining elements.
Based on the AIAG PPAP Manual (4th edition) / IATF 16949:2016 / ASME Y14.5