QualEngine Training / Engineering Change Ledger (ECN)
P2 · Training · PPAP element 02 / Table 3.1 notification cases

Engineering change ledgerEngineering Change Ledger

Definition

The engineering change ledger is the controlled registration and tracking of changes across the whole product realization process: any modification affecting product structure, material, process, tooling, location or supplier must first undergo impact assessment, then approval, then implementation, with the PFD / PFMEA / Control Plan and other controlled documents updated in step; where a PPAP Table 3.1 case applies, it is also necessary to notify the customer or resubmit. The ledger lets every change complete its loop and leave evidence behind.

IATF 16949 · 8.3.6 Design and development changes IATF 16949 · 8.5.6.1 / 8.5.6.1.1 Change control and prior approval PPAP Manual (4th edition), element 02 · Table 3.1

1. Definition and purpose

Why changes must be managed

The single largest source of risk to mass-production quality is change: a seemingly unimportant material swap, machine change or workshop move can push a previously controlled process out of control again. The core discipline of change management is —assess first, then approve, then implement; reverse the order (do it first and write the form afterwards) and the assessment is worthless.

IATF 16949:2016 clause8.5.6.1requires that changes be reviewed and actions taken (including updating output documents such as the PFMEA and Control Plan);8.5.6.1.1requires, before a process change is implemented, prior customer approval;8.3.6requires that records of design and development changes be retained and, where necessary, customer approval obtained. The 4th edition PPAP manual uses Table 3.1to list the cases in which the customer must be notified, and lists the "engineering change document" as the 2of the 18 submission elements.

Four questions the ledger must answer

QuestionAnswer given by the ledger
What changedA unique ECN number, one number per change; change content and type registered item by item
What it affectsThe impact assessment lists the drawings, PFD, PFMEA, Control Plan and work instructions affected
Customer obligationWhether it is a Table 3.1 case — notify the customer, resubmit PPAP, or no notification needed
Where it standsA five-stage closed loop of status (draft → in review → approved → in implementation → closed), with a verification record before closing

2. Change types and triggering cases

Five typical change types and the customer obligation

Determine the type first, then the obligation to the customer:whether to notify, whether to resubmit, and at what submission level. Get the type wrong and everything downstream is misaligned.

TypeTypical caseObligation and key points
Design changeAffects product structure, dimensions, material or performanceWritten approval from the customer engineering department; notify per Table 3.1 and fix the PPAP submission level
Process changeMachining method, tooling, parameters, added or removed stepsBefore implementation, obtain customer prior approval(8.5.6.1.1); PFD / PFMEA / CP upgraded in step
Material / supplier changeChanging supplier or grade with the same specificationRe-validate against the new source: material / performance tests, and a full dimensional inspection where necessary (elements 10 / 12 redone)
Location / transfer changeMoving the production site or adding a new oneTriggers a complete PPAP resubmission, including all applicable elements
Restart after production stopSupply interrupted for 12 months or moreResubmit PPAP before restart to confirm the process has not drifted

Where the customer contract or CSR specifies otherwise, follow it; when in doubt whether notification is needed, treat it as notification requiredand confirm with the customer SQE — the cost of a missed notification far exceeds that of an extra one.

Supplier-side changes

Unilateral supplier changes (material, process, sub-supplier) are a common source of sudden incoming variation. The purchasing agreement should require suppliers to give prior written noticeof changes, and incoming inspection should watch the first-article verification — the ledger is not limited to changes the organization initiates itself.

3. Five-stage closed loop

Draft → in review → approved → in implementation → closed

The status moves through five stages, each with a clear owner and exit criterion; a verification record is required before closing(first article / small batch / test report). An unapproved change must not enter implementation; a change rejected at review is retained and archived, not deleted.

Draft Draft In review In review Approved Approved In implementation Implementing Closed Closed Impact assessment: affected-document list + customer obligation judgment Implement → first article / small batch verification → evidence number registered → closed Rejected changes are retained and archived (number not deleted)
Figure 3-1 ECN five-stage closed loop and the exit criterion of each stage

Exit criterion of each stage

Draft → in reviewChange content, type and draft affected-document list are complete, with originator and date.
In review → approvedImpact assessment complete; the customer obligation (notify / resubmit) has been judged and confirmed; cross-functional sign-off comments archived.
Approved → in implementationThe new revision of the controlled document has been released (revision change + withdrawal of the old revision); production switches only once the floor and the document agree.
In implementation → closedFirst article / small batch verification passed and the evidence number registered in the ledger; customer confirmation received where a Table 3.1 case applies.

4. Linkage of controlled documents

One change, a chain of documents

A change almost never touches just one document: change a step and the PFD moves, move the PFD and the PFMEA must be re-analysed, re-analyse the PFMEA and the Control Plan must be upgraded, and when the Control Plan changes the work instruction follows. The "affected controlled documents" column of the ledger is this affected list— list every item at assessment, upgrade every item at implementation, check every item at closing.

ECN ledger Unique number · closed-loop status PFD process flow diagram Steps / material flow path upgraded PFMEA Affected steps re-analysed Control Plan CP Control method revision changed Assess → list item by item → upgrade item by item → check item by item; the revision number rises with the change and the old revision is withdrawn Where the customer requires it: work instructions / inspection specifications are upgraded in step, and MSA / capability studies are redone as needed
Figure 4-1 Change impact chain: ECN → PFD → PFMEA → CP (→ work instruction)
Linkage discipline

"Changing only the drawing and leaving the PFMEA / Control Plan alone" is the most common change-related nonconformity in audits. The test is: what characteristic, what step and what control method the change affects— if it touches any of them, the corresponding document must be upgraded and the new revision number registered in the ledger.

5. Sign-off and revision control

The ledger itself is also a controlled document

The engineering change ledger is acontrolled document(IATF 16949 7.5.3 control of documented information): the current revision is controlled, obsolete revisions are withdrawn, and revisions are recorded. None of the three may be missing:

Three-level sign-offPrepared (process / project engineer) → reviewed (department supervisor) → approved (quality / technical owner), with signature + title + date.
Revision identificationThe revision number rises with each revision (A / 0 → A / 1 or B / 0), and users only ever see the current revision.
Revision recordRevision content, date, reviser and approver are traceable for every revision.

Sign-off page style (the same one built into the workbench)

ResponsibilityName (signature)TitleDateComment
Prepared by
Reviewed by
Approved by

The sign-off order cannot skip a level: preparation must be complete before review, and review must pass before approval. After a revision, the original approver (or a delegate) approves again.

6. Common mistakes and self-test

Five frequent mistakes

① The ledger record is only written after the change has been implemented; ② only the drawing is changed while the PFMEA / Control Plan are left alone; ③ a supplier changes material unilaterally without notice; ④ after a change, production is ramped up without first-article / small-batch verification; ⑤ customer approval stays verbal and no written evidence can be produced at PPAP submission.

Self-test (5 questions)

Q1What is the basic order of change management?
Implement first, assess afterwardsassess first, then approve, then implementAssess and implement at the same time
Doing it first and writing the form afterwards makes the assessment worthless; the correct order is assess → approve → implement (IATF 8.5.6.1).
Q2If a turning operation changes its clamping method (a process change), before implementation it is necessary to
Tell the warehouse to prepare materialSwitch directly and wait until it runs smoothlyObtain prior customer approval and upgrade the PFD / PFMEA / CP in step
Before a process change is implemented, prior customer approval is required (IATF 8.5.6.1.1), and the PFD / PFMEA / Control Plan are upgraded in step.
Q3What is the correct order of the five ECN stages?
Draft → in review → approved → in implementation → closedDraft → approved → in review → closed → in implementationIn review → draft → in implementation → approved → closed
The five stages are: draft → in review → approved → in implementation → closed; a verification record is required before closing.
Q4When a supplier changes material with the same specification, the correct action is to
The specification is unchanged, so just use itRe-validate against the new source (material / performance tests, etc.), register it in the ledger and judge the customer obligationWait for a customer complaint before acting
Changing supplier with the same specification is still a change: re-validate against the new source (elements 10 / 12) and judge whether it is a Table 3.1 notification case.
Q5After the change has been implemented, what is still missing before closing?
Nothing — just close itExport and print the ledger, then it can be closedFirst article / small batch verification passed with the evidence number registered, and customer confirmation received where a Table 3.1 case applies
The exit criterion for closing is the verification evidence: first article / small batch / test report passed with the number registered, and the customer obligation closed out.

Hands-on practice: Engineering Change workbench

OpenEngineering Change workbench, register a recent real or practice change completely through the five stages, complete the three-level sign-off and export it for archiving; then return toPPAP 18-element ledgerto track the remaining elements.

Based on the AIAG PPAP Manual (4th edition) / IATF 16949:2016 / AIAG APQP Manual (3rd edition, 2024)