Engineering change ledgerEngineering Change Ledger
The engineering change ledger is the controlled registration and tracking of changes across the whole product realization process: any modification affecting product structure, material, process, tooling, location or supplier must first undergo impact assessment, then approval, then implementation, with the PFD / PFMEA / Control Plan and other controlled documents updated in step; where a PPAP Table 3.1 case applies, it is also necessary to notify the customer or resubmit. The ledger lets every change complete its loop and leave evidence behind.
1. Definition and purpose
Why changes must be managed
The single largest source of risk to mass-production quality is change: a seemingly unimportant material swap, machine change or workshop move can push a previously controlled process out of control again. The core discipline of change management is —assess first, then approve, then implement; reverse the order (do it first and write the form afterwards) and the assessment is worthless.
IATF 16949:2016 clause8.5.6.1requires that changes be reviewed and actions taken (including updating output documents such as the PFMEA and Control Plan);8.5.6.1.1requires, before a process change is implemented, prior customer approval;8.3.6requires that records of design and development changes be retained and, where necessary, customer approval obtained. The 4th edition PPAP manual uses Table 3.1to list the cases in which the customer must be notified, and lists the "engineering change document" as the 2of the 18 submission elements.
Four questions the ledger must answer
| Question | Answer given by the ledger |
|---|---|
| What changed | A unique ECN number, one number per change; change content and type registered item by item |
| What it affects | The impact assessment lists the drawings, PFD, PFMEA, Control Plan and work instructions affected |
| Customer obligation | Whether it is a Table 3.1 case — notify the customer, resubmit PPAP, or no notification needed |
| Where it stands | A five-stage closed loop of status (draft → in review → approved → in implementation → closed), with a verification record before closing |
2. Change types and triggering cases
Five typical change types and the customer obligation
Determine the type first, then the obligation to the customer:whether to notify, whether to resubmit, and at what submission level. Get the type wrong and everything downstream is misaligned.
| Type | Typical case | Obligation and key points |
|---|---|---|
| Design change | Affects product structure, dimensions, material or performance | Written approval from the customer engineering department; notify per Table 3.1 and fix the PPAP submission level |
| Process change | Machining method, tooling, parameters, added or removed steps | Before implementation, obtain customer prior approval(8.5.6.1.1); PFD / PFMEA / CP upgraded in step |
| Material / supplier change | Changing supplier or grade with the same specification | Re-validate against the new source: material / performance tests, and a full dimensional inspection where necessary (elements 10 / 12 redone) |
| Location / transfer change | Moving the production site or adding a new one | Triggers a complete PPAP resubmission, including all applicable elements |
| Restart after production stop | Supply interrupted for 12 months or more | Resubmit PPAP before restart to confirm the process has not drifted |
Where the customer contract or CSR specifies otherwise, follow it; when in doubt whether notification is needed, treat it as notification requiredand confirm with the customer SQE — the cost of a missed notification far exceeds that of an extra one.
Unilateral supplier changes (material, process, sub-supplier) are a common source of sudden incoming variation. The purchasing agreement should require suppliers to give prior written noticeof changes, and incoming inspection should watch the first-article verification — the ledger is not limited to changes the organization initiates itself.
3. Five-stage closed loop
Draft → in review → approved → in implementation → closed
The status moves through five stages, each with a clear owner and exit criterion; a verification record is required before closing(first article / small batch / test report). An unapproved change must not enter implementation; a change rejected at review is retained and archived, not deleted.
Exit criterion of each stage
4. Linkage of controlled documents
One change, a chain of documents
A change almost never touches just one document: change a step and the PFD moves, move the PFD and the PFMEA must be re-analysed, re-analyse the PFMEA and the Control Plan must be upgraded, and when the Control Plan changes the work instruction follows. The "affected controlled documents" column of the ledger is this affected list— list every item at assessment, upgrade every item at implementation, check every item at closing.
"Changing only the drawing and leaving the PFMEA / Control Plan alone" is the most common change-related nonconformity in audits. The test is: what characteristic, what step and what control method the change affects— if it touches any of them, the corresponding document must be upgraded and the new revision number registered in the ledger.
5. Sign-off and revision control
The ledger itself is also a controlled document
The engineering change ledger is acontrolled document(IATF 16949 7.5.3 control of documented information): the current revision is controlled, obsolete revisions are withdrawn, and revisions are recorded. None of the three may be missing:
Sign-off page style (the same one built into the workbench)
| Responsibility | Name (signature) | Title | Date | Comment |
|---|---|---|---|---|
| Prepared by | ||||
| Reviewed by | ||||
| Approved by |
The sign-off order cannot skip a level: preparation must be complete before review, and review must pass before approval. After a revision, the original approver (or a delegate) approves again.
6. Common mistakes and self-test
① The ledger record is only written after the change has been implemented; ② only the drawing is changed while the PFMEA / Control Plan are left alone; ③ a supplier changes material unilaterally without notice; ④ after a change, production is ramped up without first-article / small-batch verification; ⑤ customer approval stays verbal and no written evidence can be produced at PPAP submission.
Self-test (5 questions)
Hands-on practice: Engineering Change workbench
OpenEngineering Change workbench, register a recent real or practice change completely through the five stages, complete the three-level sign-off and export it for archiving; then return toPPAP 18-element ledgerto track the remaining elements.
Based on the AIAG PPAP Manual (4th edition) / IATF 16949:2016 / AIAG APQP Manual (3rd edition, 2024)