QualEngine Training / Control Plan
Part 18 · Quality Management Methods · Process Control Documents

Control Plan

Definition (DEFINITION)

A Control Plan is a structured document that describes product and process parameters, the control method for each parameter, and the reaction plan to be executed when the process or product fails. It is the master control drawing for the shop floor: it takes the PFMEA risk priorities above and feeds the work instructions and inspection specifications below. The Control Plan supports IATF 16949:2016 Clause 8.5.1.1 (Control Plan), is PPAP element 7, and is the starting point for process audits and layered audits.

One-sentence summaryThe Control Plan answers three questions:What is controlled (characteristic),How it is controlled (method / sampling),What to do when control is lost (Reaction Plan + owner). It is not a document written to be read, but an action manual for the moment the process goes out of control.
3
Format (Prototype / Pre-Launch / Production)
Safe Launch is new in the 2024 Edition
11
Header Columns (2024 Edition)
The Ownership column is added
21
Control Plan Checklist Items
The old edition had only 10 items
1
Core Tool (the 6th)
Published as a standalone manual in 2024

Purpose and Value

  • Risk lands in practice: turn the failure risks of the PFMEA into control points that can be executed on the shop floor
  • Consistency: operations, characteristics and sampling are unified across the Process Flow / FMEA / Control Plan
  • Out-of-control response: makes explicit “who does what” to contain suspect product and restore control
  • Audit Baseline: process audits (including LPA) use the Control Plan as the benchmark
  • The carrier for PPAP: the production Control Plan is element 7 of PPAP

Common Misconceptions

  • Treating the Control Plan as a record form, filled in once and never updated, out of step with the shop floor
  • The Reaction Plan states “Notify the team leader” — too vague, with no concrete containment steps
  • Sampling by time (one part per hour) rather than by production quantity
  • Special characteristics not marked, or symbols inconsistent with the drawing / PFMEA
  • Operation numbers that do not match across the Control Plan, PFMEA and Process Flow
Where the Control Plan sits in the quality tool system
Process Flow Diagram Process Flow PFMEA Process risk Control Plan The master control document for the shop floor Work instruction / inspection specification Work / Inspect Inst. Process step Risk → characteristic method → execution
Figure 1 · Process Flow → PFMEA → Control Plan → Work Instruction; the operations and characteristics of all four documents must be strictly consistent
The Six Questions the Control Plan Answers
#ProblemCorresponding Header Column
1What is controlled: which product / process characteristicsCol. 4 Characteristic
2Where it is controlled: which operation / equipmentCols. 1–3 Process / Equipment
3How it is measured: what gauge / method is usedCol. 5 Evaluation / Measurement
4How much is controlled: how many to sample and at what frequencyCols. 6–7 Sample Size / Frequency
5How it is prevented: what control method is usedCol. 8 Control Method
6What to do when control is lost: action + who is responsibleCols. 9–11 Reaction / Symbols / Owner
The Seven Steps of Control Plan Preparation
1. Draw the process flow: first have the Process Flow Diagram, establishing the operation numbers (the basis of column 1 of the Control Plan).
2. Move to PFMEA: convert process failure risks into controlled characteristics and identify the special characteristics.
3. Define characteristics: list the product / process characteristics with specifications and tolerances (column 4).
4. Select methods: determine the measurement technique, sample size, frequency by quantity and control method (columns 5–8).
5. Write Reaction Plans: every row carries “action + owner” (column 9) and can be executed immediately.
6. Mark characteristics and responsibilities: mark the special characteristic symbols (column 10) and the owner (column 11).
7. Review and release: pass the 21-item checklist, validate with Reverse FMEA / LPA, and keep approval under control.
RevisionThis page aligns with the AIAG Control Plan Manual 1st Edition (published 2024-03 as a standalone manual), replacing the Control Plan chapter of APQP 2nd Edition Appendix A and PPAP 4th Edition. IATF 16949:2016 Clause 8.5.1.1 is the mandatory basis.
ScopeThe Control Plan covers the entire manufacturing process from incoming material to shipment; the 2024 Edition further brings non-value-adding processes (transport / storage / handling) and rework / repair under control.
IATF 8.5.1.1Standard requirement: the organization shall prepare a Control Plan covering systems / subsystems / parts and materials for all production and service parts; the Control Plan must include special characteristics, state the statistical tools used, and define the reaction plan for when the process fails. The PFMEA, Control Plan and work instruction must be consistent.
Control Plan ≠ Work Instruction
DimensionControl PlanWork Instruction (WI)
Perspective“what to control, how to control it, and what to do when it goes out of control”“how to operate it step by step”
ObjectCharacteristic and RiskOperation actions and sequence
Reaction Plancontains (action + owner)Generally not included; points to the CP
LevelManagement / Engineering DocumentsExecution-Layer Documents
RelationshipsThe CP is the control basis for the WIThe WI implements the control requirements of the CP
The Three Formats of the Control Plan

The Control Plan evolves as APQP advances, producing three formats for different stages.The 2024 1st Edition adds the “Safe Launch” Control Plan, used for enhanced containment during the approximately 90-day ramp at the start of production.

ShapeCorresponding APQP stageWhen to useControl Intensity
PrototypeStages 1–2Prototype build, dimensional / performance verificationLow-frequency sampling focused on dimensions and material
Pre-LaunchStage 3Pre-launch run to verify process capabilityTightened sampling to verify MSA and Cpk
ProductionStage 4 (PPAP element 7)Formal production controlSampling by quantity + a routine Reaction Plan
Safe Launch (new)Stage 4→5 ramp periodEnhanced containment during the approximately 90-day ramp after production startadditional containment + 100% inspection, may be merged with the Pre-Launch version
How the Three Formats Evolve
Prototype Prototype Pre-launch Pre-Launch Safe Launch (approximately 90 days) Production Mass Production (PPAP element 7)
Figure 2 · The Control Plan evolves with the APQP stages; Safe Launch layers enhanced containment onto the approximately 90-day ramp after production start
Safe LaunchFor the high risk early after a new part or process enters production, additional containment is required (such as 100% inspection, tightened frequency, accelerated reaction). Its duration is about 90 days; it exits once the targets are met and may be compiled together with the Pre-Launch Control Plan.
Revision ConsistencyThe Control Plan submitted with the PPAP must be the Production edition; if it subsequently enters Safe Launch, the Control Plan must be updated under change control.
Safe Launch — detailed

Why it is needed

Early after a new part or process enters production the process is not yet fully stable and latent failures are not yet fully exposed. Safe Launch applies about 90 days of strengthened containment, safeguarding quality during the highest-risk period.

Typical Tightening Measures

  • Key Characteristics 100% inspection or tightened sampling
  • Accelerated reaction: shorten reaction time and raise the escalation level
  • Additional identification / quarantine area so that suspect batches can be traced
  • More frequent process monitoring and first-off confirmation
Exit criteriaSafe Launch is not a permanent state: it is exited once the agreed quality objectives are met (such as zero escapes, capability achieved, stable cycle time) and the customer agrees. The exit must be recorded in writing and the Control Plan reverts to the regular Production version.
Key Changes in the 2024 1st Edition Control Plan Manual (14 Items)

The 1st Edition of the AIAG Control Plan Manual, published 2024-03Published as a standalone manual, replacing the Control Plan chapter of APQP 2nd Edition Appendix A and PPAP 4th Edition. The following 14 items are the core updates compared with the previous edition.

1. Standalone manual: the Control Plan is elevated to stand alongside the sixth core tool, published as a standalone manual.
2. Safe Launch: adds an enhanced-containment Control Plan for the approximately 90-day ramp after production start, which may be merged with the Pre-Launch version.
3. Ownership column: a new “Owner” column is added to the header, clarifying the process owner / responsible role for each row.
4. Pass-Through Characteristic (PTC): Pass-Through Characteristics must be identified and a control agreement reached with the customer (the downstream process determines the effectiveness of upstream control).
5. Black Box: processes whose internal details the supplier cannot fully know must satisfy the Control Plan requirements and be agreed by the customer.
6. Verify mistake-proofing: emphasises the method and frequency for verifying the effectiveness of mistake-proofing, including the management of Red Rabbit standard samples.
7. Bring rework / repair under control: Rework / repair must have a standalone Control Plan approved by the customer; rework must also be controlled.
8. Non-value-adding processes: non-value-adding processes such as transport / storage / handling are brought under risk control.
9. Sample based on production quantity: the sampling frequency follows production quantity rather than being set by time.
10. Verify by 100% visual inspection: must be verified periodically, using customer-approved standard / limit samples.
11. Reaction Plan split into two columns: the Reaction Plan is broken down into “Action + Owner” into two columns.
12. 21-item checklist + new verification methods: the Control Plan checklist is expanded from 10 items to 21 Items; Reverse FMEA and the Layered Process Audit (LPA) are introduced as verification methods.
13. Software-based development: permits the Control Plan to be developed and managed with software (where the customer requires it).
14. Family Control Plan: Family Control Plan — a single family plan covers a family of similar parts, and part-level plans are then derived from it.
Summary of Key Changes
DimensionOld edition2024 1st Edition
Published as a standalone manualAttached to APQP / PPAPA standalone sixth core tool
ShapePrototype / Pre-Launch / ProductionAdding Safe Launch
Header Columnapproximately 10 columns11 columns (Ownership added)
Checksheet10 items21 Items
SamplingOften set by timeBy production quantity
Reaction PlanSingle descriptionAction + Owner, two columns
TipThe specific implementation of each point follows the original text of the cited 2024 1st Edition manual and the customer CSR; this page summarizes the key points and is not a verbatim translation.
Key Changes in Detail

7. Bring rework / repair under control

Rework / repair must have a standalone Control Plan approved by the customer; Rework must also be controlled, with the method, inspection and traceability made explicit so that the repair does not introduce new risk.

8. Non-value-adding processes

Transport / storage / handling add no value but affect quality (impact, mixed material, deterioration). Their risks must be identified and protection and monitoring established in the Control Plan.

13. Software-based development

Software (such as a customer-specified system) may be used to develop and manage the Control Plan, improving revision consistency and linkage efficiency, while ensuring that review / approval stays under control.

14. Family Control Plan

A Family Control Plan uses one plan to cover a family of similar parts, from which part-level plans are derived; it suits high-mix low-volume production, but derivation must ensure no characteristic is lost.

Examples of non-value-adding processes: transport / storage / handling
processTypical RisksControl within the Control Plan
HandlingImpact, drop, mixed materialDesignated equipment / route, FIFO, anti-mixing identification
StorageCorrosion, deterioration, expiryTemperature and humidity, shelf life, first in first out
TransportVibration, rain, lossPackaging specifications, protection, in-transit monitoring
Rework vs Repair
DimensionReworkRepair
DefinitionRestore conformance to the original specification (without changing the design)Repaired until usable, possibly deviating from the original specification
Control Planmust be controlled, with the method / inspection / traceability made explicitmust have a standalone Control Plan and be approved by the customer
RiskIntroduces new variationA permanent deviation is possible and requires customer recognition
ChecksheetThe 2024 Edition expands the Control Plan checklist from 10 items to 21 Items, adding checks for Safe Launch, PTC, mistake-proofing verification, the two Reaction Plan columns and Ownership; each item should be checked after preparation.
Control Plan Header: 11 Columns (2024 Edition)

The 2024 1st Edition consolidates the old approximately 10 columns into 11 Columns, the key change is the addition of ‘Owner (Ownership)” columns, and presents the Reaction Plan explicitly as the two columns “action + owner”. The 11 column definitions follow.

#Column NameEnglishHow to Complete
1Part / process numberPart / Process No.Corresponds to the operation numbers in the Process Flow Diagram and PFMEA; all three must be consistent
2Process name / Operation descriptionProcess Name / OperationWhat this operation does (e.g. injection molding, welding, final assembly)
3Machine / Equipment / Fixture / ToolingMachine / Device / Jig / ToolThe equipment and tooling used, numbered for traceability
4Characteristic (number / name / specification and tolerance)CharacteristicProduct and process characteristics, with number, name and specification / tolerance
5Evaluation / Measurement TechniqueEvaluation / MeasurementGauge / method (e.g. CMM, torque gun, visual)
6Sample sizeSample SizeSample quantity per batch (e.g. 5 parts per batch)
7Sampling frequencyFrequencyBy production quantity(e.g. every 500 parts), not by time
8Control MethodControl MethodSPC, mistake-proofing, 100% inspection, first-off / last-off checks, etc.
9Reaction Plan (action + owner)Reaction PlanConcrete containment actions + responsible role when out of control (two columns)
10Special Characteristic SymbolsSpecial Char. Symbol◇/▽ etc., consistent with the drawing and PFMEA
11Owner (Ownership)OwnershipProcess owner / responsible role for this row (new in 2024)
Column ConventionColumn convention: this training page follows the original AIAG form structure (Characteristics as one group, with a separate Control Method column), while the Control Plan CP workbench on this site organises the 11 columns to its own layout (Characteristics split into No. / Product / Process, Sample merged as size / frequency, and no separate Control Method column), so the column numbers on the two pages do not correspond one to one. When reading across pages, treat this table as the manual convention and the workbench as this site's convention; for formal submission, follow the manual's form. The column-by-column guide and the fillable workbench: see the Control Plan CP workbench.
What one row of a Control Plan looks like
Process stepOperationEquipmentCharacteristicMeasurementSampleFrequencyControl MethodReaction PlanSymbolOwner
OP30Torque tighteningServo tightening gun #2Torque 45±3 N·mTorque gun reading1 partEvery 50 partsSPC + mistake-proofing against missing tighteningQuarantine the suspect parts + notify the team leader (Mr. Zhang)◇Assembly team leader
Difference in Column CountThe old edition usually had “Reaction Plan” as a single column and left the “Owner” implicit in the operation description; the 2024 Edition makes the Owner a separate column (column 11) and explicitly splits the Reaction Plan into “action + owner”, making control responsibility clearer.
ConsistencyThe operation number in column 1 must correspond fully to the Process Flow Diagram and PFMEA — the first check point of a process audit.
Common types of “Control Method” in column 8
Control MethodDescriptionApplicable
SPCMonitor process variation with control chartsMeasurable key / significant characteristics
Mistake-proofing (Poka-Yoke)Physical or logical poka-yoke on equipment so that errors cannot escapeHigh risk of assembly errors or missed inserts
100% inspection100% inspection (commonly used for Safe Launch / special characteristics)High severity, during Safe Launch
First-off / Last-off InspectionFirst-off and last-off confirmation per shift / per die changeProcesses with frequent changeovers
In-process check / samplingSampling by quantity (not by time)General characteristics
Sampling reminderThe frequency in column 7 must follow production quantity (e.g. “every 500 parts”) rather than “hourly”; Safe Launch or special characteristics should increase the frequency, up to 100% inspection.
Control Plan Cover Sheet (Form Header Block)

In addition to the 11-column table, each Control Plan cover sheet must have a management information block to ensure traceability and control.

Information itemDescription
Part / name / specificationPart number, name, latest engineering revision level
Control Plan Number / RevisionUnique number and revision; any change requires a revision increment
ShapePrototype / Pre-launch / Production / Safe Launch
Key ContactsPrepared, reviewed, approved and customer SQE
DatePrepared / Effective Date
Customer Engineering ApprovalAttach the customer signature if required
Special Characteristics and Pass-Through Characteristics (PTC)

In a Control Plan, characteristics are divided into general characteristics and special characteristics. Special characteristics stem from processes with high severity (safety / regulatory); they must be identified and under tightened control;Pass-Through Characteristic (PTC) is a new concept emphasised in the 2024 Edition — its control effectiveness is determined by the downstream process.

Special Characteristic Identification

  • ◇ Diamond: Safety Characteristic (Safety)
  • ▽ Inverted triangle: Regulatory Characteristic (Regulatory)
  • Severity 9–10 must be identified as a special characteristic in the Control Plan
  • Symbols must agree with the drawing, DFMEA / PFMEA

Pass-Through Characteristic (PTC)

  • Pass-Through Characteristics: an upstream characteristic can only be met through a downstream process
  • Its control effectiveness is determined by the downstream process; control by the upstream alone is insufficient
  • A control agreement must be reviewed and agreed with the customer
  • e.g. a dimensional clearance can only be verified through the assembly process
Control Requirements for Special Characteristics in the Control Plan
RequirementDescription
IdentificationColumn 10 is marked with ◇/▽, with the symbol shown alongside the characteristic name
Tightened samplingThe sampling frequency for special characteristics is usually higher than for general characteristics, with 100% inspection where necessary
Reaction Planmust have concrete containment + recovery steps and a designated owner
Mistake-proofingPrefer mistake-proofing (Poka-Yoke) and confirm its effectiveness
Runs throughoutThe chain Drawing → FMEA → Control Plan → Work Instruction carries everything through without loss
Example Row for Special Characteristics in the Control Plan
Process stepOperationCharacteristicMeasurementSampleFrequencyControl MethodReaction PlanSymbolOwner
OP10Stamping / formingMounting hole position 12±0.3 mmChecking AidsFirst-off + 1Every 200 partsMistake-proofing + SPCQuarantine the last 200 inspected parts + notify Process Engineering (Mr. Li)▽Stamping team leader
OP20WeldingWeld strength (safety)Destructive test1Every 100 partsWelding parameter monitoring + destructive testStop the line + quarantine the entire batch + notify Quality (Mr. Wang)◇Welding team leader
Check againstSymbols (▽ regulatory / ◇ safety) agree with the drawing and PFMEA; every Reaction Plan contains concrete actions and an owner; frequency is by quantity, not by time.
PTC agreementA PTC must be reviewed jointly with the customer, with each party's upstream and downstream control responsibility made explicit and a written control agreement concluded; a PTC without an agreement must not go into mass production.
PTC identification and control process
1. Identify PTC The downstream determines the upstream 2. Upstream control Upstream Ctrl 3. Customer review Review 4. Control agreement Control Agreement
Figure 3 · A PTC is determined by the downstream process for upstream control effectiveness; it must be identified and a control agreement reached with the customer

How Black Box processes are controlled

Where the internal details of a process are invisible to the supplier (such as an outsourced Black Box process), the Control Plan requirements for that process must still be met: inputs, outputs, characteristics and Reaction Plans must be made explicit and agreed with the customer. Loss of control must not be tolerated just because it is “not visible”.

Reaction Plan

The Reaction Plan is column 9 of the Control Plan; the 2024 Edition requires it to be broken down into two columns, “Action” and “Owner”. Their purpose is: when the process or product goes out of control, immediately contain the suspect / nonconforming product, stop the process from producing more, and stabilise it before control is restored.

The Three Elements of a Qualified Reaction Plan

  • Contain: quarantine / identify suspect product so that it cannot reach the next operation or the customer
  • Prevent: stop the line or switch over, preventing the process from producing more nonconforming parts
  • Recover: production may only resume after the root cause is eliminated and stability is verified
  • All of the above must designate the responsible person (role / name)

Unqualified Reaction Plan (bad example)

  • Only “notify the team leader” — no concrete containment action
  • Only “adjust the equipment” — no disposition of suspect product
  • No owner — it is unclear who acts
  • No recovery criteria — there is no basis for when to resume production
Reaction Plan — Good and Bad Examples
Out-of-control situationBad example (too vague)Good example (action + owner)
Torque out of toleranceNotify the team leaderImmediately quarantine the parts assembled this shift + stop the line + notify the assembly team leader (Mr. Zhang) to re-tighten and verify; resume once SPC is stable
Dimensional driftAdjust the toolingQuarantine the last 50 inspected parts + notify Process Engineering (Mr. Li) to adjust the die; production may only resume after the first-off passes and 5 consecutive parts pass
Appearance defectSort out the defects100% visual sorting + notify Quality (Mr. Wang) to start the limit-sample comparison, and hold external shipment
Red LineThe Reaction Plan must be immediately executable. A Reaction Plan that cannot be written out means nobody acts when the process is out of control — a high-frequency process-audit nonconformity.
Verification of mistake-proofing (emphasised in the 2024 Edition)

Effectiveness verification

A mistake-proofing device is not effective merely by being installed. One must specify a verification method (such as periodically introducing known defects) and a verification frequency, confirming it can genuinely intercept errors.

Red Rabbit

Test the mistake-proofing periodically with known-defect standard samples: if it does not alarm, the device has failed and immediate reaction is required. Red Rabbit samples must be under controlled management and be numbered for traceability.

lands in the CPWhen mistake-proofing is used as the “Control Method” (column 8), the verification method, frequency and Red Rabbit management requirements must be stated in the corresponding row or an attachment; otherwise the audit will judge it as “mistake-proofing not verified”.
Escalation mechanism of the Reaction Plan
LevelTriggerAction
Front lineA single part / batch out of toleranceThe operator contains per the Reaction Plan and notifies the team leader
Middle managementRecurring / adverse trendStop the line; Quality / Process Engineering intervene; launch 8D
Senior managementInvolving safety / regulatory or customer-sideEscalate to management + notify the customer SQE, recall if necessary
EscalatableThe “owner” in a Reaction Plan must name someone with the authority to truly mobilise resources; naming only a role with no disposition authority amounts to having no escalation path.
When to Review / Update the Control Plan

The Control Plan is a dynamic document, not something compiled once and then locked. IATF 16949:2016 Clause 8.5.1.1 and the 2024 Edition manual require the Control Plan to be reviewed and updated whenever any of the following occurs.

Shipping nonconforming product: shipped product is found nonconforming; the gaps in the Control Plan must be reviewed and it updated.
Any change affecting an element: changes to the product / process / measurement / logistics / supply source / volume all require re-review.
After a customer complaint and corrective action: after a customer complaint is closed, the action must be carried into the corresponding row of the Control Plan.
Frequency set by risk analysis: review the applicability of the Control Plan at intervals determined by PFMEA / risk analysis.
Safe Launch exit / entry: when the ramp ends or a new process is introduced, update the Control Plan revision.
Deviations found by Reverse FMEA / LPA: gaps found by on-floor verification (Reverse FMEA, layered audits) must be written back into the Control Plan.
The change control that an update must follow
StepAction
Identify the triggerdetermine which of the above review triggers applies
Review the impactAssess the impact on characteristics, methods, sampling and Reaction Plans
Revised documentUpdate the Control Plan under version control, with traceable number / revision
Linked updatesUpdate the PFMEA, Process Flow Diagram and work instruction in step
Approval and releaseApproved by the owner / customer (as required) and trained before working
PPAP resubmissionWhere the case is a PPAP submission case, resubmit per Section 3
LinkageA Control Plan change almost always implicates the PFMEA and the Process Flow Diagram; keep the three documents on the “same revision, same operations, same characteristics”.
Two On-floor Verification Methods (Introduced in the 2024 Edition)

Reverse FMEA

Working backwards from actual on-floor practice: do the Control Plan / PFMEA cover all real failure modes? Any gap found is written back into the FMEA and Control Plan, forming a closed loop.

Layered Process Audit (LPA)

Managers at different levels go to the shop floor at a fixed frequency to verify line by line whether the Control Plan is being executed. Focus on whether the Reaction Plans, mistake-proofing and sampling are genuinely implemented.

RelationshipsReverse FMEA manages “whether coverage is complete”, while LPA manages “whether it is actually executed”; together they verify the effectiveness of the Control Plan and drive its update.
Error-Prone Points of the Control Plan

The following are the most common errors in Control Plan preparation and maintenance, ranked by frequency in audits.

  • InconsistentDoes not match the operations in the PFMEA / Process Flow: the operation numbers and operation descriptions do not correspond across the three documents.
  • Not markedSpecial Characteristics Not Marked: the drawing / PFMEA marks ◇/▽ but the Control Plan does not, or the symbols are wrong.
  • Too vagueReaction Plan too vague: only “notify the team leader”, with no concrete containment + recovery steps and no owner.
  • SamplingBy time rather than by quantity: writing “one part per hour” violates the 2024 Edition requirement to sample “by production quantity”.
  • Two sets of realityThe document is disconnected from the shop floor: the Control Plan states 100% inspection but it is not actually done on the floor.
  • Mistake-proofingMistake-proofing not verified: mistake-proofing was installed but with no effectiveness verification method or frequency, and no Red Rabbit samples.
  • PTCPTC without agreement: pass-through characteristics not reviewed with the customer and with no control agreement.
  • Black BoxBlack Box process without sub-supplier assurance: a process invisible to the supplier does not satisfy the CP requirements and is not agreed by the customer.
Preparation Self-check Checklist
The operation numbers are consistent across the Process Flow / PFMEA / Control Plan.
All special characteristics are identified and the symbols agree with the drawing / FMEA.
Every row's Reaction Plan contains concrete actions and an owner and can be executed immediately.
The sampling frequency follows production quantity, not time.
Mistake-proofing equipment has an effectiveness verification method / frequency and Red Rabbit sample management.
PTC has been reviewed with the customer and a control agreement reached; Black Box processes are agreed by the customer.
The Control Plan is verified against the 21-item checklist and validated with Reverse FMEA / LPA.
Two On-floor Audit Cases (anonymised)
CaseProblemRoot causeCorrection
Case A
Welding operation
The Control Plan states “first-off per shift + SPC”, but on the floor one part is actually pulled every hour by timeThe sampling frequency follows time rather than production quantity, and SPC is not genuinely runningChanged to an “every 200 parts” frequency, restore the X-bar R chart, LPA weekly checks
Case B
Assembly line
The Reaction Plan for torque out of tolerance only says “notify the team leader”; the line was not stopped for two hours after control was lostThe Reaction Plan has no concrete containment / recovery steps and no ownerRewritten as “quarantine this shift's parts + stop the line + Mr. Zhang re-tightens + resume once stable”
CommonalityBoth cases fall under “The document and the shop floor out of step”. The value of a Control Plan lies in implementation, not in looking well written.
Related Tools and Reference Documents
Authoritative SourceAIAG Control Plan Manual, 1st Edition (2024-03, published as a standalone manual); IATF 16949:2016 Clause 8.5.1.1 (Control Plan). Verifiable via aiag.org and iatfms.com.
TipThe Control Plan checklist has been expanded from 10 items to 21; the specific items follow the checklist in the 2024 1st Edition manual.

The touchstone of a Control Plan: is there someone who acts the moment control is lost?

A good Control Plan is not written to be “read”; it is written to be “used” at the moment the process goes out of control. Whether the Reaction Plan lets the shop floor contain, prevent and recover immediately is the only hard measure of Control Plan quality.

Control Plan Checklist (21 Items, 2024 Edition — Summary)

The 2024 1st Edition expands the Control Plan checklist from the old 10 items to 21 Items. The table below summarises the key items (for the complete 21 items, refer to the manual's checklist); each item should be verified after the Control Plan is prepared.

CategoryVerification Points (Summary)
overallConsistent with the operations in the PFMEA / Process Flow; revision under control; covers the entire manufacturing process
CharacteristicSpecial characteristics identified (◇/▽); PTC identified and agreed with the customer; Black Box processes agreed
methodSample by production quantity; the control method is sound (SPC / mistake-proofing / 100% inspection); mistake-proofing is verified
Reaction PlanAction + Owner are both present; immediately executable; includes containment / prevention / recovery
New formatSafe Launch is defined (where applicable); the rework / repair plan is complete and customer-approved
Responsibility and VerificationThe Ownership column is filled; Reverse FMEA / LPA verification is done; non-value-adding processes are under control
The 21 Checklist Items in Detail

The following is the item-by-item list of the 21 items, corresponding one to one with the checklist items on the Control Plan CP workbench page; it is recommended that each item be verified and the record retained once the Control Plan is prepared.

#Verification Point
1The Control Plan is approved by an authorized person, with a clear revision number and effective date
2Process numbers fully consistent with the Process Flow Diagram and PFMEA
3Every operation has a corresponding process name and operation description
4Machines / devices / fixtures / tooling are listed and match the shop floor
5Characteristic numbers correspond one-to-one with PFMEA characteristic numbers
6Product characteristics are complete; dimensions include every critical item required by the drawing
7Process characteristics cover every parameter that affects product characteristics
8Special characteristics are identified by customer symbols (column 7)
9Pass-Through Characteristics (PTC) have been passed down the supply chain to sub-suppliers
10Black Box processes are noted as guaranteed by the sub-supplier, with its evidence attached
11Evaluation / measurement technique and gauge number are listed
12MSA results for critical gauges meet the requirements and the report is attached
13Sample size and frequency match the control type and capability level
14Safety characteristics are separately identified and under tightened control
15The Reaction Plan contains specific actions, not just “sort out the defects”
16The Reaction Plan names an owner and a response time limit
17The escalation path of the Reaction Plan to containment / isolation / traceability is defined
18Every column's control activity has an owner
19The record forms for first-off inspection and in-process checks are in place
20Consistency of the Control Plan with the PFMEA, MSA and SPC has been verified
21The CP update path on change (ECN / process change) is defined
Closed-loop verificationA Control Plan is not “finished once written”: it is Reverse FMEA Work backwards to confirm coverage completeness, using Layered Process Audit (LPA) Verify on-floor implementation and write any deviation back into the Control Plan.
Terminology Quick Reference
AbbreviationFull nameMeaning
CPControl PlanThe Control Plan, the sixth core tool in the 2024 edition
PTCPass-Through Characteristicpass-through characteristics require a control agreement with the customer
Safe LaunchSafe LaunchEnhanced containment during the approximately 90-day ramp after production start
Black BoxBlack Box processA process whose internal details are invisible to the supplier but which must satisfy the CP
LPALayered Process AuditLayered Process Audit verifying that the CP is implemented
Reverse FMEAReverse FMEAWork backwards from the shop floor to confirm FMEA / CP coverage completeness
Red RabbitRed Rabbit samplesKnown-defect standard samples used to verify the effectiveness of mistake-proofing
OwnershipOwner columnThe 11th column heading new in the 2024 Edition