Production Part Approval Process (PPAP) Production Part Approval Process
PPAP is A standardized customer approval procedure, used to confirm that the supplier has Understand Correctly all customer requirements and has the ability to Continuous and stable produce conforming parts under Production conditions. Its core evidence — the sample — must come from a real production run using formal tooling, equipment, process, rate and personnel, Must not be laboratory parts or prototype-tooling parts. The AIAG PPAP Manual 4th edition (still valid before 2024) is the authoritative basis; IATF 16949:2016 clause 8.3.4.4 (product approval process) makes it a mandatory requirement.
Purpose and Value
- Confirm understanding: the supplier's understanding of the design record, specifications and special characteristics is accepted by the customer
- Confirm capability: process stable at rated rate and tooling (Cpk/Ppk meets target)
- Early interception: expose dimension, material, process and system problems before production ramp-up
- Establish the baseline: standard samples and checking aids become the baseline for subsequent incoming inspection and resubmission
- Compliance Evidence: written approval satisfying IATF 16949 8.3.4.4 and the customer CSR
Common Misconceptions
- Submit Laboratory parts / prototype-tooling parts as production parts
- Treat PPAP as A one-off document package and do not resubmit after changes
- Wrong default level: when the customer does not specify, it should be Level 3, not level 1
- Believing 'signing the PSW means approval' — The status is determined by the customer's written countersignature
- Dimensional results were measured without doing Drawing Ballooning first, causing full-dimension omissions
1. Real mass production
Samples must come from real production under production tooling, equipment, process and cycle time, in quantity sufficient to represent process capability (usually 300 pieces or per customer). Lab parts, hand-reworked parts and prototype-tooling parts are all invalid.
2. Evidence complete
The 18 elements form A traceable evidence chain: design → process → measurement → capability → physical part; a break anywhere cannot prove 'stable and conforming'.
3. Customer ruling
Whether to approve is decided by Can only be countersigned by the customer in writing. Supplier self-assessment of compliance is not approval; without approval, shipping production parts is prohibited.
4. Continuously Controlled
Approval is Status, not the end point. Any change triggering §3 resets the approval status and must be resubmitted or handled per customer requirements.
| Dimension | PPAP | Design review / phase gate |
|---|---|---|
| Points of Concern | Can the supplier produce conforming parts consistently | whether the concept / design itself is feasible |
| Source of evidence | Objective data from a real production run | Calculation, simulation, prototype verification |
| Ruling party | Customer (Purchasing / SQE) | Cross-functional team + management support |
| Trigger | The 18 Change Cases in Section 3 | APQP phase milestones |
PPAP is not an isolated tool; it is the A one-off submission action of APQP phase 4 (product and process validation), and the control plan is the Element 7 among the 18 PPAP elements. The three nest layer by layer and feed each other.
PPAP is the output gate of APQP
APQP stage 4 must produce an “effective production Control Plan” and “process capability studies”; PPAP packages all of this into an evidence package submitted to the customer. Passing PPAP means stage 4 is closed and stage 5 (feedback and corrective action) begins.
The Control Plan is the 7th element of PPAP
Among the 18 PPAP elements, element 7 is the Control Plan. At PPAP submission the control plan must be the Production version, and operations, special characteristics and reaction plans must be fully consistent with the PFMEA and process flow diagram.
| APQP stage 4 output | Corresponding PPAP Element |
|---|---|
| Valid production run (MSA, Initial Process Studies) | elements 8 (MSA), 11 (Initial Process Studies) and 14 (samples) |
| Production Control Plan | Element 7 (Control Plan) |
| Full dimensional / test data for process confirmation | elements 9 (dimensional), 10 (test) and 12 (qualified laboratory) |
| Packaging and Master Sample confirmation | elements 15 (Master Sample) and 16 (Checking Aids) |
| Stage 4 gate report | element 18 (PSW) + element 3 (Customer Engineering Approval if required) |
The supplier must submit PPAP and obtain customer approval before the first shipment when any of the following occurs. When the customer does not specify a level in writing, submit at Level 3 by default. The list below covers all major triggers in manual §3.
| # | Reason for Submission | English / key-point note |
|---|---|---|
| 1 | New part / new product | New Part / New Product — a part never supplied to this customer before, or a completely new design. |
| 2 | Engineering Change (design / purchasing / manufacturing) | Engineering Change — a design, purchasing or manufacturing change approved by customer engineering. |
| 3 | Tooling transfer / replacement / refurbishment / additional equipment | Tooling: Transfer / Replacement / Retool / Refurbish — tooling moved to another plant, replaced, overhauled or refurbished. |
| 4 | Correction (correction of previous nonconforming submission) | Correction of Discrepancy — resubmission after correcting a “discrepancy” identified by the customer. |
| 5 | Tooling idle > 12 months, production resumed | Tooling Inactive > 12 Months — production resumed after a shutdown of more than 12 months. |
| 6 | Supply source change (sub-supplier / material) | Change to Sub-supplier / Material — the sub-supplier or raw material source changes. |
| 7 | Produced by new / modified molds, equipment or processes | New / Modified Tool, Equipment, Process — first production run with new tooling, equipment or process. |
| 8 | Process change (process / method / sequence) | Change to Process — the manufacturing process, method or operation sequence changes. |
| 9 | Change to inspection / acceptance method (new technical change) | Change to Inspection / Test Method — inspection, measurement or test methods change (including technical change). |
| 10 | After correction of a dimensional / material / performance deviation | Deviation Corrected — after correcting dimensional, material or performance issues previously permitted under a deviation. |
| 11 | Bulk material composition change | Bulk Material Composition — the formulation / composition of the bulk material changes (where applicable). |
| 12 | Resumption after suspended shipment | Recovery After Shipment Suspension — resumption after the customer suspends shipments and the corrective action is verified. |
| 13 | Other cases notified or authorized by the customer | Customer Notification / Authorization — other submission cases defined by the customer CSR. |
| 14 | Part / tooling produced by new or modified resources (extended) | Part / Tool produced by new or additional sources — a new source of supply, a plant at another location, or an added production line. |
| 15 | Uses a construction or method that has been waived or superseded | Alternate Construction / Method — the original construction waived by the customer is superseded by an alternate. |
| 16 | Production at a different location / an additional site | Production from New / Additional Location — production at another plant or an additional site. |
| 17 | Tooling transferred to another supplier or returned to the customer | Tooling Returned / Transferred — tooling is handed over, returned or transferred to an external processor. |
| 18 | Other situations the customer requires a submission for | Other as Requested — other PPAP submissions requested by the customer in a formal letter. |
| Disposition | Meaning | Typical Situations |
|---|---|---|
| Must be submitted and approved | PPAP must be submitted and written approval obtained before shipment | The 18 main change cases in Section 3 (new part, tooling transfer, process change, etc.) |
| Notify the customer | Notify the customer of the change and decide per the CSR whether a submission is required | “Notification” type changes defined by the customer CSR (not requiring a mandatory resubmission of PPAP) |
| Waiver / Exemption | The customer waives the corresponding element or part in writing | Standard parts, appearance-part waivers, specified element waivers |
PPAP uses levels to control 'how much evidence to give the customer, how much to keep at the supplier for reference'. The higher the level, the more complete the evidence to the customer. Most customers default to requiring Level 3.
| Grade | Content Submitted to the Customer | Retained by the Supplier | Typical Uses |
|---|---|---|---|
| 1 | Only PSW (appearance parts with AAR) | The remaining records are retained on site at the supplier | A simplified submission for low risk / high customer trust |
| 2 | PSW + Samples + Limited supporting data | Complete data retained on site at the supplier | Cases where physical evidence is needed but not all the data |
| 3 | PSW + Samples + Complete supporting data | Master Sample / Checking Aids / CSR retained for review | Default Level, the most commonly used |
| 4 | PSW + As specified by the customer requirements | The rest are retained as the customer defines | Customer-defined element list (e.g. a specific CSR) |
| 5 | PSW + sample + full data, reviewed at Supplier Site | All held on site at the supplier for customer review | The customer performs the PPAP review on site at the supplier |
Symbol meaning: S = submit to customer and keep a copy; R = keep at supplier site, provide when customer requests; * = keep at supplier site, submit when customer requires. The table below is the authoritative AIAG PPAP 4th edition matrix; in practice follow the matrix in the referenced manual appendix.
| Element | Name | L1 | L2 | L3 | L4 | L5 |
|---|---|---|---|---|---|---|
| 1 | Design Records | R | S | S | * | S |
| 2 | Authorized Engineering Change Documents | R | S | S | * | S |
| 3 | Customer Engineering Approval (if required) | R | S | S | * | S |
| 4 | DFMEA (when the supplier has design responsibility) | R | * | * | * | S |
| 5 | Process Flow Diagram | R | R | R | * | S |
| 6 | PFMEA | R | R | R | * | S |
| 7 | Control Plan | R | R | R | * | S |
| 8 | MSA Studies | R | * | * | * | S |
| 9 | Dimensional Results | R | S | S | * | S |
| 10 | Material, Performance Test Results | R | S | S | * | S |
| 11 | Initial Process Studies | R | S | S | * | S |
| 12 | Qualified Laboratory Documentation | R | S | S | * | S |
| 13 | Appearance Approval Report (AAR) | R* | S* | S* | * | S |
| 14 | Sample Product | S | S | S | * | S |
| 15 | Master Sample | R | R | R | * | S |
| 16 | Checking Aids (key item) | R | R* | R* | * | S |
| 17 | Customer-Specific Requirements (key item) | R | R* | R* | * | S |
| 18 | Part Submission Warrant (PSW) | S | S | S | S | S |
Customer specification takes precedence
The level is usually specified in Customer purchasing document / contract / CSR. The supplier must follow the customer-specified level and must not add or drop elements on its own.
Not specified = Level 3
When the customer does not specify a level, Default Level 3. Submit PSW + sample + full data, and keep 15/16/17 at the supplier site for reference.
Below are the 18 PPAP 4th-edition submission elements. The 'Key Items' mark comes from the manual's special emphasis on elements 16 (checking aids) and 17 (customer-specific requirements); 'submit under default level 3?' follows the matrix in the previous section.
| # | Name | English | Core Content | Key Items | L3 Submission |
|---|---|---|---|---|---|
| 1 | Design Records | Design Record | Part drawings, math data and specifications, including all approved engineering changes. Bulk materials require a formulation record. | — | Yes |
| 2 | Authorized Engineering Change Documents | Authorized Eng. Change Docs | Engineering changes approved in writing by the customer but not yet incorporated into the Design Records. | — | Yes |
| 3 | Customer Engineering Approval (if required) | Customer Eng. Approval | Engineering approval evidence required by the customer at a specific stage (mandatory where noted on the drawing). | — | Yes |
| 4 | DFMEA | Design FMEA | Provided only when the supplier Holds design responsibility; includes design failure-mode analysis. | — | Retained for Review* |
| 5 | Process Flow Diagram | Process Flow Diagram | Describes the complete manufacturing process from incoming material to shipment; the operation numbers agree with the PFMEA / CP. | — | Retained for Review |
| 6 | PFMEA | Process FMEA | Analysis of potential failure modes and effects of the process, identifying special characteristics and control priorities. | — | Retained for Review |
| 7 | Control Plan | Control Plan | Production version control plan covering special characteristics, methods and reaction plans (see Part 18). | — | Retained for Review |
| 8 | MSA Studies | Measurement System Analysis | Analysis of gauge repeatability and reproducibility (%GRR), bias, linearity and stability. | — | Retained for Review* |
| 9 | Dimensional Results | Dimensional Results | Full dimensional results, entered item by item against the ballooned drawing. | — | Yes |
| 10 | Material, Performance Test Results | Material/Performance Tests | Material certificates and performance test reports, issued by a qualified laboratory. | — | Yes |
| 11 | Initial Process Studies | Initial Process Studies | Ppk (initial) / Cpk (after stabilising) capability study; key characteristics ≥ 1.67, significant ≥ 1.33. | — | Yes |
| 12 | Qualified Laboratory Documentation | Qualified Lab Documentation | Laboratory scope / accreditation certificate proving the tests were performed in a qualified laboratory. | — | Yes |
| 13 | Appearance Approval Report (AAR) | Appearance Approval Report | The Appearance Approval Report is required only for appearance parts (colour, texture, gloss) and must be signed by the customer. | — | Yes* |
| 14 | Sample Product | Sample Production | Samples from a real production run, serving as the basis for customer inspection and for the Master Sample. | — | Yes |
| 15 | Master Sample | Master Sample | The Master Sample is signed and sealed and retained until production ends or the customer releases it. | — | Retained for Review |
| 16 | Checking Aids | Checking Aids | List of gauges, fixtures and MSA and wear-prone parts (Key Items). | ★ | Retained for Review* |
| 17 | Customer-Specific Requirements | Customer-Specific Reqs | Additional requirements specified by the customer CSR (Key Items, higher priority than the general manual). | ★ | Retained for Review* |
| 18 | Part Submission Warrant (PSW) | Part Submission Warrant | A formal submission document signed by the supplier's authorized person, summarising all results and declarations (see Module 6). | — | Yes |
PPAP is not 'bundling 18 documents and sending them out' but a Controlled process from customer requirements to written approval. The 8 steps below cover the typical path from trigger to closure and align with the APQP phase-4 timeline.
An auditable submission package looks like this
- Cover: PSW (element 18) + submission reason + level + result summary.
- Design Layer: design record (1) + engineering change (2) + customer engineering approval (3) + DFMEA (4, when design-responsible).
- Process Layer: flow diagram (5) + PFMEA (6) + control plan (7) + MSA (8).
- Evidence Layer: dimensions (9) + tests (10) + initial capability (11) + qualified lab (12) + AAR (13).
- Physical Layer: sample (14) + standard sample (15) + checking aids (16) + CSR (17).
The PSW (Part Submission Warrant) is the Element 18 of the 18 PPAP elements and the 'cover and declaration' of the whole submission package. Signed by the supplier's responsible person, it assures the customer that the submitted parts come from the specified real production process and that all requirements are met.
PSW Mandatory Fields
- Part Information: part number, part name, drawing number, engineering change level, weight.
- Submission Level: clearly mark Level 1–5 (default 3).
- Reason for Submission: corresponds to the 18 situation types in §3 (new part / engineering change / tooling transfer / correction / resumption / source change / process change / other).
- Results Summary: tick by category — dimension, material, test, appearance, statistical, other — and fill the result (conforming / nonconforming / deviation).
- Declaration: formally declare that the submitted parts meet all customer requirements and that special characteristics are identified and reflected in the control plan.
- Sign: signature, date and contact of the supplier's quality responsible person / authorised representative.
| Result Category | Meaning | Completion Requirements |
|---|---|---|
| Dimensional | Full Dimensional Results | Check against the Ballooning and mark each item conforming / deviation / not applicable. |
| Material | Material Conformance | Attach the material certificate and certificate of conformance, stating grade / lot. |
| Test | Performance Test Results | Attach the qualified laboratory report, stating the test items and conclusions. |
| Appearance | colour / texture / gloss | Appearance parts must carry a signed AAR (element 13). |
| Statistical | Process capability / MSA | Enter statistical conclusions such as Ppk/Cpk and %GRR. |
| Other | Customer-specified other | Conclusions of additional evidence required by the CSR. |
| Block | Field | How to Complete |
|---|---|---|
| Part | Part number / name / drawing number / change level / weight / engineering material specification | Identical word for word to the Design Records (element 1) |
| Submit | Submission Level (L1–5) / Reason for Submission code / whether Safe Launch applies | Customer unspecified → default L3 |
| Result | Dimensional / Material / Test / Appearance / Statistical / Other | Check each item as conforming or a deviation, attaching the report number |
| Declaration | All requirements met / special characteristics identified / samples come from the specified process | Confirmation and signature by the authorized person |
| Sign | Supplier name / department / authorized signature / date / telephone | The quality manager, not an ordinary administrator |
| Customer countersignature | Approved / Interim / Rejected + date of signature | The status is determined by the customer's countersignature block |
The customer's reply to the PPAP package has only three states. Note: Production parts must not be shipped without written approval.
1. Approved
The part meets all customer requirements and the supplier may ship production parts as specified. The Master Sample and Control Plan move into a controlled state.
2. Interim Approval
Limited-time / limited-quantity shipment under limited time / limited quantity. The supplier Required completes corrective action within the limit and resubmits, otherwise it terminates at expiry. Interim approval is not 'approval'.
3. Rejected
Submission does not meet requirements, or evidence is missing / inconsistent. The supplier must correct and resubmit, Must not ship.
Principles for handling the status
Approved → move into production monitoring; Interim → carry a corrective plan and a time box; Rejected → return to zero and resubmit. All three statuses must be retained in writing and fed into the lessons-learned library.
| Status | Shipment | Corrective Action | Record requirements |
|---|---|---|---|
| Approved | May be shipped as specified | then move into production monitoring | Retain the countersigned approval + submission package |
| Interim Approval | Limited time / limited quantity | must have a clear plan and a time box | Corrective plan + resubmission milestone |
| Rejected | Shipping prohibited | Return to zero and resubmit | Rejection reason + 8D / corrective evidence |
Correct use of Interim Approval
Interim approval is Conditional concession, used when the customer needs limited shipment due to supply-chain urgency while the supplier corrects within a deadline. It Cannot turn into 'default pass'; if unresolved at expiry it terminates automatically and the submission process must restart.
The following are the most common root causes of rejection in PPAP audits, ranked by frequency and severity.
- Capability Cpk not achieved: key characteristics Cpk < 1.67, important characteristics < 1.33, or using only Ppk to fake the long-term Cpk.
- Dimensional Missing dimensions: ballooning of the drawing was not done first, causing individual dimensions to be unmeasured and inconsistent with the drawing.
- Consistent PSW Inconsistent with Data: the PSW declares conformance but the dimensional / test / capability data are inconsistent or outdated.
- Characteristic Special characteristics not fully covered: special characteristics marked on the drawing / DFMEA are missing or wrongly symbolised in the control plan or PFMEA.
- Revision Wrong Document Revision: the submitted design record or control plan is not the customer's latest approved version (including unincorporated ECRs).
- Gauges MSA %GRR out of limits: gauge repeatability and reproducibility exceeds 10% (or a stricter customer threshold), so the measurement system is unreliable.
- Grade Level mismatch: level 1 misused when the customer did not specify, missing full data; or level 5 without arranging on-site review.
- Samples Non-production parts: using lab parts / prototype-tooling parts / hand-reworked parts as production samples for submission.
| Case | Symptom | Root cause | Correction |
|---|---|---|---|
| Case A steering knuckle | Sample dimensions “conforming”, but dimensions drift out of tolerance in the first month of production | Only 8 parts were measured (not a consecutive production run), so Ppk is inflated; no 300-part consecutive capability study was done | Re-establish the real production run, take consecutive samples for Initial Process Studies, and resubmit once Cpk is achieved |
| Case B connector | The PSW declares full coverage of special characteristics, but the audit finds 2 regulatory characteristics unmarked | A drawing revision adds a ▽ characteristic, but the PFMEA / Control Plan were not updated in step | Establish a “drawing change → characteristic list → FMEA/CP” linkage so that marks are added and the submission repeated |
Special characteristics are the focus of PPAP review. Safety / regulatory characteristics must be identified throughout Drawing, PFMEA, Control Plan, PSW and reflected in the PSW results and statement.
Symbol System (AIAG Recommended)
- ◇ Diamond: Safety characteristic (Safety), failure endangers life / safety.
- ▽ Inverted triangle: Regulatory characteristic (Regulatory), failure violates government regulations.
- The customer CSR may specify dedicated symbols; the customer's requirement governs.
Requirements running throughout
- Special characteristics must be set to high severity (9–10) in DFMEA / PFMEA.
- Must be identified with the same symbol in Control Plan and tightened control.
- Must be declared identified and controlled in PSW.
- Missing or wrong marks = a direct risk of rejection.
| Where the Document Lands | Symbol marking requirements | Relationship with the PSW |
|---|---|---|
| Design Records (element 1) | Safety / regulatory characteristics marked with ◇/▽ on the drawing | The PSW must declare in the Results section that they have been identified |
| DFMEA (element 4) | Corresponding failure mode severity 9–10 | Process input where the supplier holds design responsibility |
| PFMEA (element 6) | the same symbols, and detection / prevention actions are established | The source of the special characteristics column in the Control Plan |
| Control Plan (element 7) | Marked with ◇/▽ in the characteristic column, with tightened sampling and a Reaction Plan | PPAP element 7 must be the production version and consistent |
| Work Instruction | Marked with the same symbol at the operation to prompt the operator | Evidence of On-floor Execution |
| PSW (element 18) | Declares that special characteristics have been identified and reflected in the Control Plan | The “overall declaration” of the submission package |
APQP — Advanced Product Quality Planning
PPAP is a one-off submission action in APQP stage 4; APQP closes with PPAP approval as the marker.
See Part 16Control Plan
PPAP element 7; the 2024 1st Edition is a standalone manual and is the starting point for process audits.
See Part 18PFMEA / Process Flow Diagram
PPAP elements 5 and 6; the operation numbers must agree with the Control Plan.
MSA Studies
PPAP element 8; dimensions may only be measured after gauge %GRR is verified acceptable.
Treating PPAP as an “approval gate” rather than a “document package”
The real risk does not lie in whether the PSW was signed, but in whether the real production process is genuinely stable. A five-step self-check before submission — “Ballooning → capability → consistency → revision → sample origin” — avoids 90% of rejections.
| Abbreviation | Full name | Meaning |
|---|---|---|
| PSW | Part Submission Warrant | Part Submission Warrant, PPAP element 18 |
| AAR | Appearance Approval Report | Appearance Approval Report, element 13 |
| MSA | Measurement System Analysis | Measurement Systems Analysis, element 8 |
| CSR | Customer-Specific Requirements | Customer-Specific Requirements, element 17 |
| Ballooning | Drawing Ballooning | Number every dimension on the drawing for full dimensional verification |
| Ppk / Cpk | Initial / Process Capability Index | Output of the capability study; key ≥ 1.67, significant ≥ 1.33 |
| %GRR | Gauge Repeatability and Reproducibility | Core MSA metric, normally ≤ 10% |
| Interim | Interim Approval | Concessionary shipment with limited time / limited quantity |