Datum system: locking the part6 degrees of freedom · A|B|C

A rigid body has 6 degrees of freedom in space (3 translations + 3 rotations). Each DOF has two directions, but directions are not DOF — the datum system's job is to constrain these 6 DOF in order and lock the part's posture — The order A | B | C is the order in which the part is located in the assembly: the primary locating face is most stable with the largest contact, then orientation, last position. Also note: a datum is not the actual face of the part but ideal geometry — established by a datum simulator (plate, mandrel, sphere) in maximum contact with the actual datum feature; the gauge's supporting surface is the physical realization of the simulator (expanded in PE-03).

The three roles of a datum

  • Assembly datum: which faces/holes locate the part in the assembly
  • Inspection datum: what the gauge/CMM uses to simulate
  • Machining datum: where the fixture presses

Unifying all three is the gold standard for datum design — if datums are not unified, a 'transformation error' appears in the tolerance stack-up.

Common errors

  • Using a non-functional face as A (only because it's easy to machine/measure)
  • The datum sequence does not match the assembly sequence
  • The datum feature itself has no form tolerance (the datum face is crooked)
  • Multiple datum reference frames on one drawing are independent of each other
Enter: The 3-2-1 Principle →
3-2-1 rulePlane · Line · Point

Primary datum face 3 contact points lock 3 DOF (1 translation + 2 rotations), secondary datum 2 points lock 2 more, tertiary datum 1 point locks the last — this is 3-2-1.

Primary locating face A (3 points) · front viewA1A2A3PartThree points locate a plane: constrains Z translation + X/Y rotationsSecondary locating B (2 points) · tertiary locating C (1 point) · side viewB1B2Two points locate a line: constrains Y translation + Z rotationsC1One point locates a plane: constrains X translation → all 6 DoF fully constrainedInspection, fixturing and assembly follow the same sequence: A first, then B, then C
3-2-1 locating: face A 3 points (Z translation + X/Y rotation), face B 2 points (X translation + Z rotation), face C 1 point (Y translation). All six DOF locked; measurement and assembly reproduce the same constraints.

Why 3-2-1 is mandatory

Over-constraint (4 points pressing one face) makes the part 'seesaw' on the gauge — the result depends on how it sits. 3-2-1 guarantees The part has a unique orientation on the fixture: anyone measuring, anywhere, gets the same result. For flexible sheet-metal parts, datum targets (next section) are also needed to fix the 'soft' surface.

Enter: Datum Targets →Back to the Datum Reference Frame →
Datum targetsHow to fix soft surfaces

Sheet-metal and molded surfaces are naturally uneven. Building a datum on the whole face, the result drifts with the part's deflection posture. Datum targets 'pin' the datum to specified points/lines/surfaces — the gauge supports only these targets, so the posture is unique.

Datum targets on a casting blank (ISO 5459)CastingA1A2A3B1C1● Point targets: three ball-end contacts locate datum A— Line target: two section lines (generatrices)▭ Surface target: local small plane (pin/block)Symbol: circle split top/bottom — ID on top, size below;A1 / A2 / A3 together form a single datum A
Datum targets: A1–A3 point targets, B1–B2 line targets, C1 surface target. The target symbol is a circle split top/bottom — ID (A1) on top, target size below; point targets have the lower half filled, line targets end in ×, surface targets are hatched rectangles. Gauge supports correspond one-to-one. EV-Box top-cover sealing zone uses 3 point targets to build datum A.

Review Points

① target position should be at Actual contact points of the fixture / assembly; ② point/line/surface target dimensions must be marked (gauge spherical support diameter); ③ targets must not be on free zones that will later deform; ④ non-rigid parts (sheet-metal covers like this) are marked per ISO 10579 distinguishing free state / restrained state — measure the flexure in free state Ⓕ; datum targets usually work with the restrained state.

Enter: Tolerance Principles →Back to 3-2-1 →
Tolerance principleIndependent · Envelope · Ⓜ · Ⓛ

What is the relation between size and geometric tolerance? That is what the tolerance principle answers — choose wrong and the acceptance conclusion is directly reversed.

Envelope requirement (⚡ ASME default / marked Ⓔ)Ø10.00 (size OK)The ring gauge will not pass → rejectMMC boundary: size and form act as oneIndependence principle (ISO / GB default)0.05Ø10.00 (size OK)Bend ≤ 0.05 → acceptSize and form are verified independently of each otherThe same bent pin, two rules give opposite conclusions — at drawing review, first confirm the tolerance principle.
Envelope vs independence compared: envelope (left) size limit is the boundary, size OK auto-limits form error; independence (right) size and geometry are verified separately, not linked.
PrincipleMeaningWhen to use⚠ Standard Differences
Independence principle (ISO/GB default)Size and geometry are accepted independently of each otherWhen function and size are uncoupled (most scenarios)ISO/GB default; ASME defaults to the envelope requirement
Envelope Requirement ⒺThe actual feature must not exceed the maximum material boundaryLimit fit of clearance shaft-hole (guarantee minimum clearance)ISO requires the Ⓔ symbol explicitly; ASME applies it by default
Ⓜ Maximum Material Requirement (MMR)Geometric tolerance gains bonus when departing from MMCHole position of clearance joint (free assembly)ISO 2692 calls it MMR; ASME calls it MMC
Ⓛ Least Material Requirement (LMR)Bonus at departure from LMC (protect wall/strength)Guarantees minimum wall thickness and edge distanceISO 2692 calls it LMR; ASME calls it LMC
Virtual condition VC and the two boundaries (arithmetic behind Ⓜ — the origin of Ø6.25 in PE-01)
Hole: VC = MMC − t → Ø6.5 − 0.25 = Ø6.25  Shaft: VC = MMC + t
MMB = the MMC boundary of the datum feature (no geometric tolerance; the datum's float range)
MMVB = maximum material virtual boundary of the tolerated feature, MMC ± t (working surface of the fixed GO gauge)

Judgement rule of thumb

Assembly must 'fit' → Ⓜ (fit clearance trades for tolerance); function must 'not penetrate wall' → Ⓛ; function independent of size → independence principle; limit fit (min clearance of pin-hole is a hard constraint) → envelope requirement. Ⓜ is prohibited in zero-clearance / interference fits — without clearance there is no physical source of bonus.

Two often-missed points

① Independence ≠ form is uncontrolled — without a marked form tolerance the form error is uncontrolled; back it up with a general tolerance (e.g. ISO 2768-fH) and state it on the drawing; ② ISO 2692 also defines the reciprocity requirement Ⓡ: used together with Ⓜ/Ⓛ, unused geometric-tolerance allowance can flow back to the size tolerance (no such symbol in ASME).

Enter: Key Points →Back to Datum Targets →
Advanced: 3-2-1 locating and datum orderDatums are not chosen arbitrarily

Datum order A→B→C is not a numbering habit; it is the physical order of 'which face rests first, then which, last which is pressed' in gauge / fixture / assembly. Its engineering embodiment is 3-2-1 locating:

DatumConstrained degrees of freedomContact pointsCorresponds on the EV-Box
Primary datum A3 translations + rotations3 points (largest plane)Flange sealing face of the frame
Secondary datum B2 translations + rotation2 points (long edge)One locating edge of the frame
Tertiary datum C1 translation1 point (short-edge end)One end of the frame

Swapping A/B reorders the whole tolerance chain and may scrap the gauge. So PE-00 says 'datum order is the GD&T information most easily overlooked by newcomers'.

Gauge input differences: independence vs Ⓜ/Ⓛ (ASME terminology in brackets)

PrincipleGauge TypeDesign input
Independence (ASME: RFS)Variable gauge / CMM point-by-pointNo boundary; judged by the true value
Ⓜ Maximum Material RequirementFixed-boundary GO gauge (Ø6.25)The virtual condition boundary is constant
Ⓛ Least Material RequirementFixed boundary limit gaugeUsed for wall thickness / minimum clearance

Decision rule of thumb

To 'guarantee assembly' use Ⓜ (fixed GO gauge is cheapest); to 'guarantee minimum wall/strength' use Ⓛ; else default to the independence principle, but don't omit marking and let the supplier interpret.

Advanced annotations: datum shift · simultaneous requirement · common datum

① Datum shift: when the datum feature also carries Ⓜ, the datum may float within its MMB and the tolerated feature's zone shifts with it — automatic under ISO 2692; ASME requires an explicit Ⓜ after the datum letter (e.g. AⓂ). ② Simultaneous requirement: whether several tolerance frames on one DRF must be met simultaneously — ISO defaults to separate requirements and needs the SIM annotation for simultaneity; ASME defaults to simultaneous for a pattern on the same DRF. ③ Common datum A-B: two features (e.g. two coaxial bores) are simulated jointly and share one common axis as a single datum, noted A-B — distinct from the sequential A|B|C datum system.

Key Points & ChecklistTake Away on One Page
A | B | C = the assembly locating sequence: first ask 'how is this part located in the assembly', then set the datum.
The datum feature itself must be accurate: give the datum face a form tolerance, otherwise the datum itself is floating.
3-2-1 prevents over-constraint: gauge posture must be unique for the measurement to be reproducible.
Use datum targets on soft surfaces: target position = fixture/assembly contact point, and mark the target dimension.
The three datums are unified: inconsistent assembly/inspection/machining datums produce a transformation error entering the tolerance chain.
Choose the tolerance principle by function: fit → Ⓜ; no wall penetration → Ⓛ; unrelated → independence; limit fit → envelope.
First understand the difference between the two systems: ISO defaults to independence, ASME to envelope; ask the system before reading.

Take Away in One Sentence

Datum system = Use the assembly sequence to lock the degrees of freedom: A|B|C constrains the 6 DOF in order, 3-2-1 guarantees unique posture, datum targets fix soft surfaces, tolerance principle answers 'who governs size vs geometry'.

Further Reading

  • PE-03 Inspection and Verification — how the datum is simulated on the gauge/CMM.
  • Standards: ISO 5459 (datum), ISO 2692 (Ⓜ/Ⓛ), ISO 8015 (independence default), GB/T 16671.

© 2026 PanShu / 潘书 · QualEngine | PE-02 training page.